Greyhound Way Construction & Traffic Impacts | October 19–November 6
Posted Date: 10/12/26 (04:33 PM)

Beginning Monday, October 19, 2026, at 8:30 AM, construction crews will begin installing a new fire line connection for the Schweitzer Wellbeing Center on Greyhound Way. Work is expected to be completed by November 6, 2026, barring unforeseen delays.
The construction schedule has been coordinated to minimize disruptions to the public.
Anticipated Traffic Control Schedule:
- October 19–20: Greyhound Way open with traffic revisions (TCP A)
- October 21 (8:30 AM)–October 23: Greyhound Way closed to all traffic. Use detours. (TCP D)
- October 24–November 1: Greyhound Way open with traffic revisions (TCP A)
- November 2–4: Greyhound Way open with traffic revisions (TCP B & C)
- November 5–6: Greyhound Way closed to all traffic (TCP D)
Please plan ahead and anticipate potential delays during construction!